Job Analysis 6.82
Table of Contents
Job Analysis 6.82
This tab allows for a complete over view of your whole contract including: contract summary, Cash flow, billing information, Project Costs, budget, commitments, costs to date, cost to complete and profit.
Contract Summary
Original Value |
---|
Represents the total amount quoted on this contract job.
Approved Variations |
---|
Variations on the contract that have been marked as approved.
Current Value (Ex Tax) |
---|
The sum of the original value and approved variations.
Cash Flow Summary
Cost To Date (Payments Made) |
---|
All payments you have made on the overall cost on this contract.
Payments Made |
---|
Generates the total of how much the customer has paid off on this contract.
Positive (Negative) Cash Flow |
---|
This will inform you if the cash flow for this job. The total will either be positive or negative. There for the total will show if the contract has a negative cash flow or a positive.
Billing Information
Billed To Date |
---|
This total generates the amount in a dollar figure of how much you have invoiced on this contract job.
GST |
---|
This is ten percent of the above “Billed To Date” total.
Total Inc Tax |
---|
This calculates the total of “Billed To Date” with the GST amount included.
Less Payments To Date |
---|
Current total amount of cash receipts received.
Balance Outstanding |
---|
The total amount that the customer is owing on this contract job to the current date.
Balance To Be Invoiced (Ex Tax) |
---|
The total amount that customer still needs to be invoiced for.
Retained |
---|
The total value of all retention of all invoices on this job.
Include Unbilled Retention |
---|
This option located at the top right hand corner of the Job Analysis allows you to include the retention total that has not been billed.
Budget
Original Budget |
---|
The original total set for costs on the contract job.
Variations |
---|
The amount originally estimated the cost of all variations would be.
Total Budget |
---|
The total of the budget up to the current date.
Commitments |
---|
Displays the total amount dedicated towards commitments e.g. back orders.
Cost To Date
Materials + Contractors |
---|
The total of parts used and time entered on this job up to this date will be shown here.
Labour |
---|
List all the labour costs on this contract up to the current date.
Total Costs to Date |
---|
The total of all cost on this contract up to this date.
Cost To Complete
Cost To Complete |
---|
Generates the total cost left to complete the contract job.
Cost To Complete (Inc Commitments) |
---|
This generates the same total as above but also includes outstanding commitments as well.
Over Run |
---|
This field will let you know how much against your initial budget you have over run.
Under Run |
---|
Displays how much extra profit you have accumulated as a total price.
Profit
Profit To Date |
---|
Displays your total profit up to this date.
Profit % |
---|
Displays the total amount of profit as a percentage against the total of your over all price and profit together.
Budgeted Profit |
---|
Gives you the estimated amount of profit on your contract job.
Budgeted Profit % |
---|
This is the total profit accumulated but in a percentage. It’s calculated against the cost and profit of the contract job.
Budget Markup % |
---|
Generates the percentage of a markup against the total of the whole contract job.